Multiple Choice
All of the following items are generally considered when selecting the right type of contract EXCEPT:
A) extent of price competition
B) overall degree of cost and schedule risk
C) urgency of requirements
D) project organization's accounting system
Correct Answer:

Verified
Correct Answer:
Verified