Figure 141 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31

Question 7

Multiple Choice

  Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)  -Consider the project performance report presented in figure 14.1.As a project manager,these results should lead you to...​  A)  take actions to understand and remedy the schedule performance on the active avionics work packages.  B)  take actions to understand and resolve budgetary overruns on the active communications work packages.  C)  take actions to understand and remedy the schedule performance on the active training work packages.  D)  notify the project owner that you will not require all of the funding currently budgeted for this project. Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)
-Consider the project performance report presented in figure 14.1.As a project manager,these results should lead you to...​ 


A)  take actions to understand and remedy the schedule performance on the active avionics work packages. 
B)  take actions to understand and resolve budgetary overruns on the active communications work packages. 
C)  take actions to understand and remedy the schedule performance on the active training work packages. 
D)  notify the project owner that you will not require all of the funding currently budgeted for this project.