Many Organizations Require the Completion of a Project Close-Out Report

Question 13

Multiple Choice

Many organizations require the completion of a project close-out report upon completion of a project.These reports typically include which of the following? 


A)  a review of the project's original justification 
B)  a list of team members dismissed due to poor performance 
C)  transcripts of team member conversations 
D)  review of team building exercises

Correct Answer:

verifed

Verified