Multiple Choice
Many organizations require the completion of a project close-out report upon completion of a project.These reports typically include which of the following?
A) a review of the project's original justification
B) a list of team members dismissed due to poor performance
C) transcripts of team member conversations
D) review of team building exercises
Correct Answer:

Verified
Correct Answer:
Verified