Multiple Choice
Which of the following is not true about a critical path in a project network with certain activity times?
A) Activities on the critical path have the least slack.
B) The longest activity in the project must lie on the critical path.
C) There can be several critical paths in a project network.
D) The first activity in the network is always on the critical path.
Correct Answer:

Verified
Correct Answer:
Verified