Multiple Choice
Assessing control risk at a lower level most likely would involve:
A) changing the timing of substantive procedures by omitting interim testing and performing the tests at year-end.
B) identifying specific internal controls relevant to specific assertions.
C) performing more extensive substantive procedures with larger sample sizes than originally planned.
D) reducing inherent risk for most of the assertions relevant to significant account balances.
Correct Answer:

Verified
Correct Answer:
Verified
Q28: The auditor must understand internal control before
Q29: After completing the preliminary phase of the
Q30: Data capture occurs through source documentation, direct
Q31: The auditor's communication of material weaknesses in
Q32: A substantive strategy is used when control
Q34: Trumpeter Corporation is a small publicly traded
Q35: What are four potential tools available to
Q36: Internal control includes monitoring of controls.
Q37: If auditors conduct substantive procedures as of
Q38: Proper segregation of functional responsibilities in an