Earned Value Is Based on the Concept That the Percentage

Question 9

Multiple Choice

Earned value is based on the concept that the percentage of project completion is closely correlated with __________.


A) the number of levels in the project
B) relevance of the project
C) cost or the use of resources
D) final assembly of the output