Short Answer
The Tuckman ladder suggest that teams progress through four development phases.Those phases are listed below.Match each phase with its description.
A)Forming
B)Storming
C)Norming
D)Performing
1)Teams function as a cohesive unit focused on accomplishing the goals of the project.
2)Team members come together for the first time and begin learning about their roles and responsibilities.
3)In this phase,the team members begin to establish team norms and team cohesiveness develops.Individual team members reconcile their behaviors to support the overall team,and trust develops.
4)Work on the project begins,but initially the team members tend to work independently,which often leads to conflict.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: A project manager must make trade-off decisions
Q7: The _ is a person who spearheads
Q8: The project manager needs _ credibility.<br>A)technical and
Q9: The ability to sense conflict early,then confront
Q10: The project manager's responsibilities are broad and
Q12: A _ is a person who helps
Q13: Which of the following is not typically
Q14: The project manager should be more skilled
Q15: The _ represents everything outside the system
Q16: During the buildup stage of a project