Multiple Choice
Agile IT project teams are typically __________ and located at __________.
A) large,a single site
B) small,multiple sites
C) large,multiple sites
D) small,a single site
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A _ must be submitted for any
Q3: RACI stands for<br>A)responsive,accountable,consult,inform<br>B)responsible,accountable,consult,inform<br>C)responsive,accountable,consult,integrate<br>D)responsible,admissible,consult,integrate
Q4: Once the project charter is completed and
Q5: When the project is to deliver a
Q6: A useful tool for facilitating the management
Q7: Identify four important outcomes associated with the
Q8: Which of the following is not another
Q9: This element of the project plan contains
Q10: When using a WBS,all of the work
Q11: The _ chart is a tree diagram