    __________ States That Adding Manpower to a Late Software Project
Solved

__________ States That Adding Manpower to a Late Software Project

Question 42

Question 42

Multiple Choice

__________ states that adding manpower to a late software project makes it later.


A) Brooks' Law
B) Murphy's Law
C) Smith's Law
D) The Rule of Thumb

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q37: If projects include repetitive tasks with significant

Q38: In order to develop a budget,the project

Q39: If a project budget is over funded,it

Q40: Several issues face firms preparing bid proposals,particularly

Q41: A work element in the project plan

Q43: Suppose that a person requires eight hours

Q44: A work element in the project plan

Q45: _ issues are present when bidders "low

Q46: The allowance for contingencies is usually in

Q47: Overhead costs are all of the following

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines