menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 8: Scheduling
  5. Question
    What Type of Time Estimates Are Used in the Critical
Solved

What Type of Time Estimates Are Used in the Critical

Question 18

Question 18

Multiple Choice

What type of time estimates are used in the critical path method?


A) Deterministic
B) Probabilistic
C) Most likely
D) Average

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: Any time two or more paths of

Q14: Explain the difference between total slack and

Q15: Most commercially available project management software applications

Q16: Which of the following is not an

Q17: All of the following are possible conditions

Q19: In the AOA network,arrows depict _.<br>A)networks<br>B)events<br>C)activities<br>D)dummy activities

Q20: The shortest time in which the entire

Q21: The variance of a population is a

Q22: Describe the benefits of forming a network

Q23: In a network,if the delay of an

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines