In the AOA network,circles depict ________.
A) networks
B) events
C) logical dependencies
D) dummy activities
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q25: A(n)_ is a specific task or set
Q26: Assume that task J has a most
Q27: Task F has duration of 10 days
Q28: Slack is also known as _.<br>A)critical path<br>B)scope<br>C)float<br>D)precedence
Q29: In CPM,an activity can be conducted at
Q31: Describe the process for determining the critical
Q32: The arrangement of all activities (and,in some
Q33: The _ chart shows planned and actual
Q34: On method of managing the uncertainty is
Q35: The basic approach of all scheduling techniques