Multiple Choice
Project task E has the following estimates: (1) optimistic time - 10 days (2) Pessimistic time - 20 days,and (3) Most likely time - 12 Days.The expected time using the beta statistical distribution is __________ days.
A) 9
B) 13
C) 15
D) 22
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: _ law suggests that work expands to
Q2: The _ was developed by Henry Gantt
Q4: The authors,when discussing networks,describe a(n)_ as the
Q5: Critical path method (CPM)has primarily been used
Q6: With simulation,the model is repeated many times
Q7: Explain the meaning of slack in a
Q8: The critical activities in real-world projects typically
Q9: _ is one possible way to check
Q10: The difference between the late start and
Q11: Project task E has the following estimates: