Multiple Choice
The critical ratio control chart uses a ratio made up of two parts -- the ratio of actual progress to scheduled progress,and the __________.
A) ratio of earned value to planned cost
B) ratio of budgeted cost to actual cost
C) ratio of actual cost to budgeted cost
D) ratio of planned cost to earned value
Correct Answer:

Verified
Correct Answer:
Verified