Multiple Choice
During the implementation of project closure,if personnel performance evaluations are required,they should be prepared by the __________.
A) closure manager
B) senior manager
C) project manager or immediate supervisor of the team member
D) project management office
Correct Answer:

Verified
Correct Answer:
Verified
Q22: In closure by integration,project assets are _.<br>A)liquidated<br>B)reassigned
Q23: It is important to select a project
Q24: Describe the subjects that should be addressed
Q25: The project performance of the final report
Q26: Special _ managers are sometimes useful in
Q28: Listed below are four critical success factors
Q29: These closures are a result of conflicts
Q30: The _ of the final project report
Q31: Most studies have shown that the factors
Q32: During the implementation of project closure,the closure