Multiple Choice
company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project)
A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days