Multiple Choice
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The valuations in an Earned Value Management
Q18: In CPM analysis, it is generally expected
Q32: Project management software available today combines CPM
Q39: Calculating the early start and early finish
Q53: project can be subdivided into which of
Q57: project starts out as which of the
Q58: Below are the data for a Time-Cost
Q61: disadvantage of a matrix project organizational structure
Q63: One of the advantages of a functional
Q100: One of the assumptions made using CPM