Solved

You Have Collected the Data for a Time-Cost CPM Scheduling

Question 56

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?   A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500


A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions