Solved

In a Project Analysis Using Three Time Estimates with More

Question 24

Multiple Choice

In a project analysis using three time estimates with more than one critical path existing, how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?


A) The project manager averages the variances and uses that.
B) The project manager uses the smallest variance in order to get the highest probability of on-time completion.
C) The project manager uses the variances considered most correct.
D) The project manager uses the largest variances in order to understate the probability of on-time completion.
E) The project manager uses the most likely estimate plus the amount of slack time in the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions