Multiple Choice
In a project analysis using three time estimates with more than one critical path existing, how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?
A) The project manager averages the variances and uses that.
B) The project manager uses the smallest variance in order to get the highest probability of on-time completion.
C) The project manager uses the variances considered most correct.
D) The project manager uses the largest variances in order to understate the probability of on-time completion.
E) The project manager uses the most likely estimate plus the amount of slack time in the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: You are looking at a chart that
Q21: Below are the data for a Time-Cost
Q25: A simple project listing of five activities,
Q33: CPM is an abbreviation for critical path
Q36: A matrix project attempts to blend properties
Q60: You have just used the network planning
Q69: Using the Time-Cost CPM model, the crash
Q72: The critical path in a CPM analysis
Q89: In a CPM analysis, if you subtract
Q99: An advantage of a pure project where