The major goal of Critical Path analysis is to:
A) Estimate the project's completion date
B) Identify and manage the critical path
C) Determine the latest feasible start date
D) Provide a visual aid that indicates precedent and antecedent relationships
E) To determine when each activity in the project should be scheduled
Correct Answer:

Verified
Correct Answer:
Verified