Multiple Choice
Jones hired Smith,a general contractor,to build a garage as an addition to Jones' home,located in Pennsylvania.Smith hired Adam to do the roofing work on this garage.All the work was done satisfactorily,and at the completion of the work,Jones paid Smith the agreed price.However,Smith never paid Adam for his work.Three weeks after Adam finished his work,he filed a mechanics' lien against the property and demanded that Jones pay him for his work.Which of the following is most correct under the Pennsylvania system?
A) Jones need not pay Adam because he has already paid in full for the garage.
B) Jones need not pay Adam because Adams' contract is actually with Smith in this case.
C) Jones should pay Adam because Adam has the right of redemption.
D) Jones should pay Adam because he can enforce his lien claim against the property.
Correct Answer:

Verified
Correct Answer:
Verified
Q63: When a rug repairer fixes a damaged
Q64: Explain the difference between an accommodation surety
Q65: Who are party to a deed of
Q66: Miguel has been complaining to his neighbor
Q67: A party who borrows money to buy
Q69: A subcontractor is a person who contracts
Q70: Under the Pennsylvania system,the general contractor's failure
Q71: Why is a guaranty contract similar to
Q72: A surety has a right of _,which
Q73: Tina cosigns a promissory note at Globe