Multiple Choice
Which of the following managers are most likely to use the critical path method?
A) managers in charge of scheduling the production runs on an assembly line
B) managers in charge of scheduling and monitoring activities involved in major projects
C) managers in charge of finding the best location for a production facility
D) managers in charge of product design and testing
Correct Answer:

Verified
Correct Answer:
Verified