Which of the Following Is Not a Budgeting and Scheduling

Question 35

Multiple Choice

Which of the following is not a budgeting and scheduling approach for managing a project?


A) program evaluation and review technique (PERT)
B) critical evaluation and review technique (CERT)
C) critical path method (CPM)
D) graphical evaluation and review technique (GERT)