The Process Design Team at a Manufacturer Has Broken an Assembly

Question 12

Multiple Choice

The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.They work a 7 hour day and want to produce at a rate of 360 units per day.What should their takt time be? The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.They work a 7 hour day and want to produce at a rate of 360 units per day.What should their takt time be?   A)  70 seconds B)  65 seconds C)  52 seconds D)  25 seconds


A) 70 seconds
B) 65 seconds
C) 52 seconds
D) 25 seconds