The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above. What is the takt time?
A) 53.3 seconds
B) 67.5 seconds
C) 75.8 seconds
D) 90 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q78: The process design team at a
Q79: These three tables show the floor
Q80: Use this scenario for the following
Q81: Use this scenario for the following
Q82: In a supply chain, the output from
Q84: _ gets its name from the fact
Q85: The shorter the required takt time, the
Q86: A mass lecture for 500 freshmen in
Q87: The back room refers to the part
Q88: Use this scenario for the following