The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above. The process engineer calculates the takt time and examines the task times indicated in the table. He decides to use the minimum cycle time instead and have the workers leave early each day once they have built 400 units. How much earlier would the workers leave?
A) 12 minutes and 53.3 seconds
B) 14 minutes and 20 seconds
C) 16 minutes and 40 seconds
D) 18 minutes and 15 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q83: Use this scenario for the following
Q84: _ gets its name from the fact
Q85: The shorter the required takt time, the
Q86: A mass lecture for 500 freshmen in
Q87: The back room refers to the part
Q89: The Devon Tower graces the Oklahoma City
Q90: Which poses the greatest underlying managerial challenges
Q91: What is a cellular layout and what
Q92: Why are process decisions important?
Q93: A collection of different departments must be