Multiple Choice
Use this scenario for the following questions.
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above.How many workers must be added to increase the output rate to one unit per minute?
A) 1
B) 2
C) 3
D) 4
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A legal service in a corporate acquisition
Q21: What is the optimal location for these
Q24: Takt time sets the upper limit on
Q34: Use this scenario for the following
Q52: Use this scenario for the following
Q55: According to the law of variability, converting
Q87: The back room refers to the part
Q96: Use this scenario for the following
Q98: Products that are customized only at the
Q100: Use this scenario for the following