Use this material requirements planning record to explain how kanbans and MRP can be used together.This plant operates on a 40-hour week,and uses a 10% safety factor on a container size of 20 units with a half-day turnaround time on a container.What features of each system should be used and for what purposes?
Use this material requirements planning record to explain how kanbans and MRP can be used together.This plant operates on a 40-hour week,and uses a 10% safety factor on a container size of 20 units with a half-day turnaround time on a container.What features of each system should be used and for what purposes?

Correct Answer:

verifed

Verified

Companies that use both MRP and kanbans ...