    What Is the Latest That Activity D Can Start If
Solved

What Is the Latest That Activity D Can Start If

Question 23

Question 23

Multiple Choice

What is the latest that activity D can start if A lasts 5 days,B lasts 7 days,C lasts 4 days,D lasts 5 days,E lasts 7 days,and F is 6 days long? What is the latest that activity D can start if A lasts 5 days,B lasts 7 days,C lasts 4 days,D lasts 5 days,E lasts 7 days,and F is 6 days long?   A)  14 B)  15 C)  16 D)  17


A) 14
B) 15
C) 16
D) 17

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q14: The budget estimates made during the concept

Q22: A hatmaker, fresh off a very successful

Q22: Activities on the critical path may have

Q28: What is the latest that activity B

Q42: The earliest start time of an activity

Q47: For critical path activities, slack is equal

Q57: The tablet unearthed by the archaeologist

Q63: The actual work gets done during the

Q64: An activity's duration added to its earliest

Q65: The earliest finish time of an activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines