Multiple Choice
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.What is the cheapest crash cost for the project if the contractor must complete all work in 45 days?
A) $550
B) $950
C) $1150
D) $1450
Correct Answer:

Verified
Correct Answer:
Verified