Multiple Choice
What is the NPV of a project that costs $100,000, provides $23,000 in cash flows annually for six years, requires a $5,000 increase in net working capital, and depreciates the asset straight line over six years while ignoring the half-year convention? The discount rate is 14%.
A) -$15,561
B) -$13,283
C) $13,283
D) $15,561
Correct Answer:

Verified
Correct Answer:
Verified