Multiple Choice
A decision tree shows a 30 percent probability of $2 million in returns and a 70 percent chance of $1 million in returns.What is the maximum you would invest today in this project if the cash in-flow occurs one year in the future and the discount rate is 10 percent?
A) $818,182
B) $1,181,818
C) $1,300,000
D) $1,363,636
Correct Answer:

Verified