Multiple Choice
When is it appropriate to include sunk costs in the evaluation of a project?
A) Include sunk costs when they are relatively large
B) Include sunk costs if it improves the project's NPV
C) Include sunk costs if they are considered to be overhead costs
D) It is never appropriate to include sunk costs
Correct Answer:

Verified
Correct Answer:
Verified