Multiple Choice
What is the approximate maximum amount that a firm should consider paying for a project that will return $15,000 annually for 5 years if the opportunity cost is 10 percent?
A) $33,520
B) $56,860
C) $62,540
D) $75,000 PV = $15,000
Correct Answer:

Verified
Correct Answer:
Verified