If the opportunity cost of capital for a project exceeds the Project's IRR, then the project has a(n) :


A) Positive NPV
B) Negative NPV
C) Acceptable payback period
D) Positive profitability index

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Because of deficiencies associated with the payback

Q24: How is the profitability index calculated and

Q25: When choosing among mutually exclusive projects, the

Q32: Jamieson is considering a 5-year, $250,000 project

Q34: If the NPV of a project is

Q38: When hard capital rationing exists, projects may

Q39: The "gold standard" of investment criteria refers

Q41: A project has a payback period of

Q42: A project can have as many different

Q94: A project costing $20,000 generates cash inflows

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines