When Calculating a Project's Payback Period, Cash Flows Are Discounted

Question 126

Multiple Choice

When calculating a Project's payback period, cash flows are discounted at:


A) The opportunity cost of capital
B) The internal rate of return
C) The risk-free rate of return
D) A discount rate of zero