Multiple Choice
What is the NPV break-even for a project costing $4,000,000 and generating cash flows according to .30 *sales - $450,000? Assume the project will last 10 years and requires a discount rate of 12 percent.
A) $2,093,654
B) $2,359,047
C) $3,859,798
D) $13,783,333 5.6502(.3 sales - 450,000) = 4,000,000
1) 69506 sales - 2,542,590 = 4,000,000
1) 69506 sales = 6,542,590
Correct Answer:

Verified
Correct Answer:
Verified