Multiple Choice
The cost to rework a defective product before it is shipped out from the factory would be classified as which cost of quality category?
A) Prevention costs
B) Appraisal costs
C) Internal failure costs
D) External failure costs
Correct Answer:

Verified
Correct Answer:
Verified