A company must invest in project 1 in order to invest in project 2. Which of the following constraints ensures that project 1 will be chosen if project 2 is invested in?


A) X1 + X2 = 0
B) X1 + X2 = 1
C) X1 -X2 \ge 0
D) X1 -X2 \le 0