Solved

If a Company Selects Project 1 Then It Must Also \ge

Question 47

Multiple Choice

If a company selects Project 1 then it must also select either Project 2 or Project 3. Which of the following constraints enforces this condition?


A) X1 - X2 -X3 \ge 0
B) X1 + (X2 - X3) \le 0
C) X1 + X2 + X3 \le 2
D) X1 - X2 - X3 \le 0

Correct Answer: