Multiple Choice
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
-The purpose of the backward pass in the Critical Path Method (CPM) technique is to
A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: Exhibit 15.5<br>The following questions use the information
Q27: Exhibit 15.4<br>The following questions are based on
Q28: Exhibit 15.2<br>The following questions employ the AON
Q29: Exhibit 14.13<br>The following questions use the information
Q30: Exhibit 15.2<br>The following questions employ the AON
Q32: Exhibit 15.5<br>The following questions use the information
Q33: Exhibit 15.6<br>The following questions use the information
Q34: Exhibit 14.13<br>The following questions use the information
Q35: Exhibit 15.4<br>The following questions are based on
Q36: Exhibit 15.4<br>The following questions are based on