Projects differ from classic organizational processes because projects are:
A) Discrete activities.
B) Part of line organization.
C) Well established systems in place to integrate efforts.
D) Multi-objective.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q63: An information system project might be assessed
Q64: The emergence of global markets has made
Q65: The most basic level in Kerzner's project
Q66: Maynard and Zed construct a spider-web diagram
Q67: A product is introduced into a market,gains
Q69: The ability to learn a concept and
Q70: The dimension of project success that is
Q71: Acme uses no recognizable project management processes
Q72: The MBA redesign committee presents the results
Q73: Project management is a useful training ground