Multiple Choice
Which of the following statements about project success criteria is BEST?
A) Project cost is an external performance measure.
B) Completion time is an internal performance measure.
C) Client acceptance is an internal performance measure.
D) Client acceptance is often referred to as conducting a "quality" check.
Correct Answer:

Verified
Correct Answer:
Verified