Question 65

Multiple Choice

The Larson and Gobeli study that compared projects that had been managed in a variety of structural types revealed that new product development projects tended to be MOST effectively executed when the organizational structure was a:


A) Project matrix.
B) Project organization.
C) Balanced matrix.
D) Functional matrix.

Correct Answer: