Multiple Choice
In a partnership,each member of the project team is responsible for the project's outcomes and the current situation,whether it is positive or shows evidence of project problems.The term that BEST describes this responsibility is:
A) Exchange of purpose.
B) A right to say no.
C) Joint accountability.
D) Absolute honesty.
Correct Answer:

Verified
Correct Answer:
Verified