Multiple Choice
One consequence of conceptual development that proceeds with a problem that is poorly understood is:
A) Problem restatement.
B) Cost overruns.
C) Problem clarification.
D) Task confusion.
Correct Answer:

Verified
Correct Answer:
Verified