Multiple Choice
Any measurable,tangible,verifiable outcome,result,or item that must be produced to complete a project or part of a project is a:
A) Product.
B) Deliverable.
C) Tangible.
D) Work product.
Correct Answer:

Verified
Correct Answer:
Verified