Multiple Choice
In order to allocate costs more precisely,a company will assign:
A) Bar codes to each activity.
B) Activity codes to each subdeliverable.
C) WBS codes to each activity.
D) Level 4 codes to each package element.
Correct Answer:

Verified
Correct Answer:
Verified