Multiple Choice
All pieces of a project must be developed and assembled to produce the final product functionality.Designing,making,and assembling these components is the role of:
A) Configuration management.
B) Baseline scope control.
C) Systematic management.
D) Baseline configuration.
Correct Answer:

Verified
Correct Answer:
Verified
Q88: Organizational breakdown structure (OBS)allows companies to:<br>A)Assign the
Q89: The Scope Management chapter begins and ends
Q90: A statement of work identifies:<br>A)A need.<br>B)A project
Q91: The section of the contractual documentation that
Q92: Scope reporting not only identifies the type
Q94: An earned value report shows:<br>A)How much money
Q95: The framing crew would never know when
Q96: Sustainability is focused solely on the long-term.
Q97: Project team members can identify whom should
Q98: If viewed from a flow standpoint,the stage