Question 21

Multiple Choice

Which of the following phenomena would be most likely to occur if the project team did NOT have clear and commonly understood project goals?


A) The motivation level of team members would increase.
B) Conflict among team members would increase.
C) The level of trust among team members would increase.
D) The interdependency among team members would increase.

Correct Answer: