Multiple Choice
Disruptive acts of some project team members due to personality issues,hidden agendas,or interpersonal problems are categorized as:
A) Poor communication.
B) Lack of motivation.
C) Dysfunctional behavior.
D) Poor leadership.
Correct Answer:

Verified
Correct Answer:
Verified