Multiple Choice
Project risk is highest during the:
A) Finish phase of the project life cycle.
B) Conceive phase of the project life cycle.
C) Execute phase of the project life cycle.
D) Develop phase of the project life cycle.
Correct Answer:

Verified
Correct Answer:
Verified